- It is invented by the Joseph Aspdin in 1824. But the credit for the invention of the modern Portland cement goes to his son William Aspdin in 1840s.
Raw Materials for PC
Chemical Composition of Portland Cements
In the cement, the oxide content is about 90%. The oxide composition of ordinary Portland cement is given below:
S.no
|
Item
|
Percentage
|
1.
|
CaO
|
63.6
|
2.
|
SiO2
|
20.7
|
3.
|
Al2O3
|
6
|
4.
|
Fe2O3
|
2.4
|
5.
|
SO3
|
1.4
|
6.
|
MgO
|
2.4
|
7.
|
Na2O
|
0.1
|
8.
|
K2O
|
0.7
|
9.
|
Loss on ignition
|
1.3
|
10.
|
Insoluble residue
|
0.3
|
11.
|
Free CaO
|
1.1
|
Name
|
Chemical formula
|
Abbreviation
|
Percentage
|
Tricalcium silicate
|
3CaO.SiO2
|
C3S
|
51
|
Dicalcium silicate
|
2CaO.SiO2
|
C2S
|
23
|
Tricalcium aluminate
|
3CaO.Al2O3
|
C3A
|
8
|
Tetracalcium aluminoferrite
|
4CaO.Al2O3.Fe2O3
|
C4AF
|
9
|
1. Tricalcium silicate
It hardens rapidly on addition of water and responsible for initial set and early strength.
2. Dicalcium silicate
It hardens slowly. The effect of C3S on strength increases with ages beyond one week.
3. Tricalcium aluminate
In first few weeks, it contributes in strength development. It hydrates first among all four compounds of the PC. Since it produces high heat and also reacts with soils and water that contains moderate to high sulfate concentrations, it is considered as the least desirable component of the PC.
4. Tetracalcium aluminoferrite
It hydrates very rapidly but contributes very little to the strength of the concrete. It lowers clinkering temperature i.e. temperature at which clinker is formed.
Manufacturing of Portland Cement (PC)
- First the raw materials obtained from the source is reduced to fine particle size.
- The raw materials are blended and mixed in such a manner that it produces uniform chemical composition containing Calcium carbonate (CaCO3), silica (SiO2), alumina (Al2O3), iron oxide (Fe2O3) etc.
- Now the blended raw mix is heated to a temperature at which all the moisture from it escapes out as steam or water vapor.
- The dried raw mix is heated to 8000C. At this temperature what happens, the calcium carbonate gets dissociated into calcium oxide (known as free lime) and carbon dioxide which escapes out as gas.
- As the temperature rises above 8000C, the formation of principal active compounds of Portland cement starts. And the completion of this process takes place at 1400-16000C. Final product that we get is PC clinker. Usually 1 ton of clinker is produced from 1.8 tons of raw material.
- The cement clinker so produced is cooled to a temperature of 60 to 1500C and then stockpiled.
- After that the clinker is ground to specified fineness by adding small amount of gypsum. The gypsum added controls the setting time of finished cement.
- Finally the finished cement is stored in silos for a short period of time before it is being sent to the customers.
- Crushing, screening and stockpiling of raw materials.
- Proportion calculation of raw materials.
- Preparation of raw mix by blending
- Feeding of raw mix into rotary kiln.
- 100 C: Evaporation of free water.
- 150-300 degree C: Evaporation of more firmly bounded water.
- 600 degree C: MgCO3 —–> MgO + CO2
- 900 degree C: CaCO3 —–> CaO + CO2
- Reaction between lime and clay starts.
- 1300 degree C: Initiation of major compound formation.
- 1400-1600 degree C: completion temperature (clinker forms having C3A, C2S, C3S, C4AF)
- Cooling and storage of clinker.
- Clinker is ground with gypsum.
- Storing and marketing of cement.